Client Name
Moy Park Dungannon

Project Location
Moy Park Ltd, Killyman road, Dungannon

Project Information
Project lasted two years and was carried out in phases within a live factory environment. RBB were involved in the completion of chicken processing plant to increase weekly capacity from 1.2 million birds to 2.0 million birds processed and dispatched, construction works comprised of: Construction of 10 m high chill store (12,500 sqft), ancillary block (6,500 sqft), office block and operatives canteen (6,500 sqft), plant room area (1,000 sqft), bespoke gate house (1,000 sqft), internal live bird transfer / processing areas / Holima area (30,000 sqft), dispatch (6,000 sqft) and new 400 vehicle car park.